Which of these is NOT an input of the estimate activity durations process?

  1. Resource calendars

  2. Project budget

  3. Activity resource requirements

  4. Risk register

The correct answer is: Project budget

The estimate activity durations process is used to determine the amount of time needed to complete each activity in a project. This helps in creating a realistic schedule and timeline for the project. Option A - Resource calendars are used to identify the availability of resources and their planned vacations or time off, which can have an impact on the duration of an activity. Option C - Activity resource requirements refer to the specific resources needed to complete a particular activity, which is crucial in estimating the duration of the activity. Option D - The risk register is used to identify potential risks and their likelihood and impact on the project timeline, which can affect the estimated duration of activities. Therefore, the correct answer is B, as the project budget is not directly related to estimating the duration of activities in a project.