CAPM (Certified Associate in Project Management) 2026 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 885

What is an output of the estimate costs process?

Activity cost estimates

The correct answer is A. Activity cost estimates.

During the estimate costs process, one of the key outputs is the activity cost estimates. This output provides the estimated costs for each activity within the project, which is essential for developing an accurate project budget.

The other options are not outputs of the estimate costs process. The project charter is created during the develop project charter process, while the final project report is a final deliverable at the end of the project. Stakeholder register updates are typically outputs of processes related to stakeholder management but not specifically the estimate costs process.

Get further explanation with Examzify DeepDiveBeta

Project charter

Final project report

Stakeholder register updates

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy