Which of these is an input of the develop project team process?

  1. Resource calendars

  2. Budget forecasts

  3. Stakeholder register

  4. Risk management plan

The correct answer is: Resource calendars

Resource calendars are an input to the Develop Project Team process because they provide information on resource availability and help in assigning resources to project activities. This process involves building a team by acquiring the project team members needed to complete project activities. Resource calendars are essential for determining the availability of team members and their skill sets, which is crucial for successfully executing the project. The other options, budget forecasts, stakeholder register, and risk management plan, are typically not inputs to the Develop Project Team process.