Which of the following is NOT an input of the determine budget process?

  1. Scope baseline

  2. Risk management plan

  3. Activity cost estimates

  4. Project schedule

The correct answer is: Risk management plan

The correct answer is B. The Risk Management Plan is NOT an input of the Determine Budget process. In the Determine Budget process, the inputs include the Scope Baseline (choice A), Activity Cost Estimates (choice C), and Project Schedule (choice D). These inputs are used to establish the cost baseline against which project performance can be monitored and controlled. The Risk Management Plan, on the other hand, is not directly used in determining the budget for the project. It focuses on identifying, analyzing, and responding to project risks, which is a separate process from determining the project budget.