Which of the following is NOT a tool or technique of the acquire project team process?

  1. Pre-assignment

  2. Budget analysis

  3. Negotiation

  4. Multicriteria decision analysis

The correct answer is: Budget analysis

The acquire project team process deals with obtaining and assigning resources to the project. Pre-assignment, negotiation, and multicriteria decision analysis are all techniques that can be used to acquire the necessary resources for a project. However, budget analysis is not a tool or technique used in this process. Budget analysis is typically used in the cost management process, which focuses on monitoring and controlling the project's budget. Therefore, it is not a part of the acquire project team process.