Which of the following is an output of control stakeholder engagement?

  1. Stakeholder notifications

  2. Change requests

  3. Work performance data

  4. Project charter

The correct answer is: Change requests

Change requests are an output of control stakeholder engagement because during this process, stakeholders may request changes to the project scope, requirements, or other project aspects. By engaging with stakeholders and considering their feedback, new requirements or modifications may be identified, leading to the generation of change requests. This process is crucial for ensuring that stakeholder needs and expectations are addressed appropriately throughout the project lifecycle. Stakeholder notifications (Option A) are typically associated with the Manage Stakeholder Engagement process, where project information is distributed to stakeholders based on their communication needs. Work performance data (Option C) is an output of the Monitor and Control Project Work process, not specifically a direct output of control stakeholder engagement. The project charter (Option D) is a foundational document created during the Develop Project Charter process and is not directly related to the control stakeholder engagement process.