What is the purpose of inspection in project management?

  1. To allocate resources efficiently

  2. To determine if deliverables have been properly delivered

  3. To assess team performance

  4. To review the project budget

The correct answer is: To determine if deliverables have been properly delivered

Inspection in project management is the process of evaluating project deliverables to ensure they meet the agreed-upon requirements and quality standards. It involves conducting a thorough review of the work that has been completed so far and comparing it against the project plan and objectives. This helps to identify any errors or discrepancies and allows for corrective action to be taken promptly, thus ensuring that the project stays on track and meets its goals. While the other options may be important factors in project management, they do not directly pertain to the purpose of inspection. Option A refers to resource management, which is a crucial aspect of project management, but not the main purpose of inspection. Option C pertains to team performance, which is monitored throughout the project, but not the main focus of inspection. Option D addresses the financial aspect of project management, but again, not the main purpose of inspection. Therefore, the most appropriate answer is B, as it directly relates to the purpose of inspection in project management.