What is the purpose of the control schedule process?

  1. To expand the project scope

  2. To monitor status of project activities and manage changes to the schedule baseline

  3. To reduce project costs

  4. To increase project team efficiency

The correct answer is: To monitor status of project activities and manage changes to the schedule baseline

The purpose of the control schedule process is to monitor the status of project activities and manage changes to the schedule baseline. This process helps ensure that the project stays on track in terms of timelines and milestones. Options A, C, and D are incorrect because they do not accurately describe the specific purpose of the control schedule process in project management.