What is the purpose of earned value management?

  1. To exclusively track the costs of a project

  2. Used to monitor the progress of a project and is an analytical technique

  3. To determine the profitability of a project

  4. To track the number of resources used in a project

The correct answer is: Used to monitor the progress of a project and is an analytical technique

Earned Value Management (EVM) is a widely-used project management technique that integrates the scope, schedule, and cost of a project. The primary purpose of EVM is to monitor the progress of a project by comparing the actual work completed to the planned work and the actual costs incurred to the planned costs. It provides project managers with a comprehensive view of project performance, allowing them to identify variances early and take corrective actions to keep the project on track. Thus, choice B is the correct answer as it accurately reflects the purpose of earned value management.