What is the process of plan schedule management?

  1. The method of tracking, reviewing, and reporting project progress

  2. The process of identifying the project tasks and responsibilities

  3. The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

  4. The technique of estimating the amount of effort and time the project will take

The correct answer is: The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

The process of plan schedule management refers to the activities involved in establishing the policies, procedures, and documentation for all aspects of planning, developing, managing, executing, and controlling the project schedule. This includes defining the project schedule, identifying project tasks and responsibilities, tracking and reporting project progress, and estimating the amount of effort and time needed for the project. Option A and B are incorrect because they only refer to specific aspects of schedule management and do not encompass the entire process. Option D is also incorrect because it only mentions one part of the process, estimating the time and effort, and does not include other important elements such as planning and controlling the schedule.