What is the main goal of the validate scope process?

  1. To control project scope

  2. To confirm successful project delivery

  3. To develop the project team

  4. To finalize the project budget

The correct answer is: To confirm successful project delivery

The main goal of the validate scope process is to confirm the successful delivery of the project's defined scope. This involves reviewing and verifying deliverables with stakeholders to ensure they meet the agreed upon requirements. Option A, controlling project scope, is more closely related to the verify scope process, which focuses on monitoring and managing changes to the project scope. Option C, developing the project team, is part of the human resource management aspect of the project, while option D, finalizing the project budget, is part of the cost management aspect. These options are not the main goal of the validate scope process and are therefore incorrect.