CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the key goal of prevention in a process?

  1. Fixing errors once they've been identified

  2. Keeping errors out of the hands of the customer

  3. Maintaining a continuous scale of performance

  4. Keeping errors out of the process

The correct answer is: Keeping errors out of the process

The key goal of prevention in a process is to keep errors out of the process. By focusing on preventing errors from occurring in the first place, a project can save time, resources, and effort that would otherwise be spent on fixing errors after they have already occurred. This proactive approach helps streamline the process and ensures a higher level of quality in the end product or service. Option D is the correct choice because it directly addresses the primary objective of prevention in project management. On the other hand: - Option A, fixing errors once they've been identified, is a reactive approach rather than a preventive one. - Option B, keeping errors out of the hands of the customer, focuses on the end result rather than the internal process of error prevention. - Option C, maintaining a continuous scale of performance, is not directly related to the key goal of prevention, which is to avoid errors in the process.