What is the goal of taking a proactive decision regarding cost of conformance?

  1. To reduce environmental impact

  2. To increase customer base

  3. To eliminate errors from a project and product

  4. To speed up production time

The correct answer is: To eliminate errors from a project and product

Taking a proactive decision regarding cost of conformance means to implement measures that prevent errors and defects from occurring in a project or product. This in turn helps to save time, resources, and money by avoiding the need for rework or corrective actions. Options A, B, and D would only be potential byproducts of implementing cost of conformance measures, but they are not the primary goal or purpose. The goal is to improve the quality and efficiency of a project or product by minimizing errors and defects.