What is one of the outputs of the conduct procurements process?

  1. Selected sellers

  2. Quality metrics

  3. Risk management plan

  4. Communications management plan

The correct answer is: Selected sellers

One of the outputs of the conduct procurements process is selected sellers, and this is the best answer because it accurately reflects the purpose of the process. Conduct procurements involves evaluating potential sellers and selecting the most suitable ones to provide the necessary goods or services for a project. Options B and C, quality metrics and risk management plan, are incorrect because they are outputs from other processes in project management. Quality metrics are typically defined in the quality management process, while risk management plan is typically created in the plan risk management process. Option D, communications management plan, is also incorrect as it is an output of the plan communications management process.