What is NOT a focus of Project Human Resource Management?

  1. Acquiring Team Members

  2. Releasing Team Members

  3. Managing Costs

  4. Leading the Project Team

The correct answer is: Managing Costs

Project Human Resource Management is responsible for managing people in a project so that the project can be completed successfully. Acquiring Team Members, Releasing Team Members, and Leading the Project Team are all aspects of managing people within a project. Managing Costs, on the other hand, is a focus of Project Cost Management. This involves developing and controlling the project budget and ensuring that resources are used effectively and efficiently. While managing costs may indirectly impact human resources, it is not the primary focus of Project Human Resource Management.