What is an output of the control communications process?

  1. Resource allocation plan

  2. Change requests

  3. Budget forecasts

  4. Stakeholder register

The correct answer is: Change requests

The correct answer is B - Change requests. During the control communications process, the project team evaluates the performance of the project communications against the communications management plan. If there are any deviations or issues identified during this evaluation, it may result in the need for change requests to be initiated. Change requests are formal proposals to modify any document, deliverable, or baseline within the project. They are an essential output of the control communications process as they help in managing and implementing necessary changes to improve project performance. The other options: A. Resource allocation plan - This is not a direct output of the control communications process but rather relates more to resource management. C. Budget forecasts - Budget forecasts are more related to cost management and not a direct output of the control communications process. D. Stakeholder register - The stakeholder register is a document that identifies stakeholders and their information. It is not an output of the control communications process specifically.