What is a characteristic of resource smoothing?

  1. Changes the critical path of the project

  2. Does not change the critical path of the project

  3. Eliminates the need for resources

  4. Guarantees project completion within deadline

The correct answer is: Does not change the critical path of the project

Resource smoothing is a technique used in project management to adjust the activities within a project schedule in a way that does not impact the critical path of the project. By shifting resources or activities within a project without affecting the critical path, resource smoothing helps in optimizing resource utilization without extending the project timeline. Therefore, the correct characteristic of resource smoothing is that it does not change the critical path of the project. Option A is incorrect because resource smoothing is specifically designed to make adjustments without altering the critical path. Option C is incorrect because resource smoothing aims to optimize resource allocation rather than eliminate the need for resources. Option D is incorrect because resource smoothing does not guarantee project completion within the deadline, as other factors can still impact the overall project timeline.