What does project staff assignments documentation typically include?

  1. Budget allocations for each team member, timelines, risk assessments

  2. Project team directory, memos to team members, names inserted into project management plan

  3. Project charter details, stakeholder analysis, communication plans

  4. Resource calendars, detailed scope statements, work breakdown structures

The correct answer is: Project team directory, memos to team members, names inserted into project management plan

Project staff assignments documentation typically includes the project team directory which lists the names and roles of each team member, as well as memos to team members for important updates or changes. Option A includes budget allocations and timelines, which are not typically included in project staff assignments documentation. Risk assessments are also not typically included in this type of documentation. Option C includes project charter details and stakeholder analysis, which may be included in the overall project documentation, but not specifically in the staff assignments. Option D includes resource calendars and work breakdown structures, which are also not typically included in project staff assignments documentation. Detailed scope statements may be included, but they are not the main focus of this type of documentation. Therefore, option B is the best answer.