CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What defines the critical path of a project?

  1. The path with the shortest duration within the project

  2. The path with the highest cost activities within the project

  3. The path with the longest duration within the project

  4. The path with the most significant risks within the project

The correct answer is: The path with the longest duration within the project

The critical path of a project is defined as the sequence of tasks that must be completed in order to finish the project within its scheduled time. This means that any delay in the critical path tasks will result in a delay in the overall project completion. Option A is incorrect because the critical path is not necessarily the shortest duration, but rather the longest duration as it includes all necessary tasks. Option B is incorrect because the critical path is not determined by cost, but rather by the sequence of tasks. Option D is incorrect because while significant risks may impact the project, they do not necessarily determine the critical path. Overall, the critical path is determined by the longest duration of tasks, ensuring that the project can be completed on time.