CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What defines a category of projects with shared components unique to other categories?

  1. Project Management Information System

  2. Application Area

  3. Change Management

  4. Data Analysis

The correct answer is: Application Area

Application Area is the correct answer because it refers to a category of projects with common components and characteristics that differentiate it from other project categories. Application areas represent areas of specialization such as IT, construction, healthcare, etc., and define the unique features and requirements of projects within that specific field. This distinction helps project managers to apply specialized knowledge, tools, and techniques that are relevant and specific to the particular application area they are working in. Project Management Information System (A), Change Management (C), and Data Analysis (D) are not the most appropriate choices in this context as they do not directly define a category of projects with shared components unique to other categories like Application Area does in project management.