CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What are the types of meetings?

  1. Project kickoff, status update, and closeout

  2. Information exchange, brainstorming/option evaluation/design, decision making

  3. Scrum, Kanban, and stand-ups

  4. Negotiation, conflict resolution, and team building

The correct answer is: Information exchange, brainstorming/option evaluation/design, decision making

The correct answer is B. Information exchange, brainstorming/option evaluation/design, decision making. This is because meetings can generally be categorized into these three types: information exchange (such as project status updates), brainstorming/option evaluation/design (to generate ideas or make choices), and decision-making (where conclusions or resolutions are reached). Option A is incorrect because it lists specific project-related meetings (project kickoff, status update, and closeout) rather than broadly categorizing types of meetings. Option C is incorrect as it mentions specific Agile methodologies and daily stand-up meetings, which are not types of meetings in a general sense. Option D is incorrect because it lists specific types of activities (negotiation, conflict resolution, team building) that can occur within meetings, but these are not overarching types of meetings themselves.