What are the outputs of 'close project or phase' process?

  1. Project schedule and cost forecasts

  2. Final product/service/result and organizational updates

  3. Risk management plan and project charter

  4. Stakeholder engagement plan and quality metrics

The correct answer is: Final product/service/result and organizational updates

This process marks the end of a project or phase and involves finalizing all activities and completing the necessary documentation. Option A is incorrect as the outputs of this process do not include the project schedule and cost forecasts. Option C is incorrect as the risk management plan and project charter are already defined and approved in earlier processes. Option D is incorrect as the outputs of this process are unrelated to the stakeholder engagement plan and quality metrics. The correct outputs of the 'close project or phase' process are the final product, service, or result, along with organizational updates such as lessons learned, project review reports, and project closure documents.