What are the outputs of define activities?

  1. Scope statement, WBS, project charter

  2. Activity list, activity attributes, milestone list

  3. Project schedule, project budget, risk register

  4. Work performance data, change requests, updates

The correct answer is: Activity list, activity attributes, milestone list

The outputs of define activities are the activity list, activity attributes, and milestone list. These outputs are crucial as they provide a detailed breakdown of the project activities, their characteristics, and key milestones that must be achieved. They help in organizing and planning the project activities effectively, ensuring a smooth execution of the project. Option A is incorrect as the scope statement, WBS, and project charter are typically outputs of other processes such as Develop Project Charter and Create WBS. Option C is incorrect as the project schedule, project budget, and risk register are typically outputs of processes like Develop Schedule, Determine Budget, and Identify Risks. Option D is incorrect as work performance data, change requests, and updates are outputs of processes like Control Quality, Perform Integrated Change Control, and Monitor and Control Project Work.