CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What are outputs of the develop project team process?

  1. Project charter updates

  2. Team performance assessments

  3. Risk register updates

  4. Cost management plans

The correct answer is: Team performance assessments

The correct answer is B: Team performance assessments. During the Develop Project Team process, the primary output is the assessment of the team's performance. This assessment helps project managers understand the strengths and weaknesses of the team members, identify any areas that need improvement, and determine how well the team is functioning together. By evaluating team performance, project managers can address any issues, provide necessary training, or make changes to improve overall team effectiveness. While project charter updates, risk register updates, and cost management plans are important outputs in project management processes, they are not the direct outputs of the Develop Project Team process. The main focus of the Develop Project Team process is to enhance the performance and effectiveness of the project team members.