During risk reassessment, what should be reviewed?

  1. The budget and resources

  2. Key risks, changes, any new risks

  3. Technical accomplishments

  4. The amount of contingency reserves

The correct answer is: Key risks, changes, any new risks

During risk reassessment, key risks should be reviewed to determine if there are any changes or new risks that have emerged. Options A and D may be relevant in the overall risk management process, but they are not specifically related to risk reassessment. Option C is not directly related to risk at all.