CAPM (Certified Associate in Project Management) 2025 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 885

What does a negative Schedule Variance (SV) indicate?

The project is exactly on schedule

The project is ahead of schedule

The project is behind schedule

A negative schedule variance (SV) indicates that the project is behind schedule. This means that the actual progress of the project is lagging behind the planned schedule. This could be due to delays in completing certain tasks or unexpected obstacles that have caused the project to fall behind its timeline. Options A and B are incorrect because they suggest that the project is on or ahead of schedule, respectively. Option D is also incorrect because it refers to budget rather than schedule.

Get further explanation with Examzify DeepDiveBeta

The project is over budget

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy