CAPM (Certified Associate in Project Management) 2026 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 885

What does an SPI greater than 1.0 indicate?

Costs are over budget

Project is behind schedule

Project is ahead of schedule

An SPI (Schedule Performance Index) greater than 1.0 indicates that the project is ahead of schedule. The Schedule Performance Index is a metric used to measure the efficiency of schedule performance on a project. An SPI value greater than 1.0 means that the project is progressing ahead of the planned schedule, as the index represents the ratio of work accomplished to the work planned to be accomplished at a specific point in time. This is a positive indication for the project as it shows that the project is progressing faster than originally anticipated.

Get further explanation with Examzify DeepDiveBeta

Costs are below budget

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy