CAPM (Certified Associate in Project Management) 2025 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 885

What does estimate to complete (ETC) refer to?

Original budget for the project

Costs saved during the project

The estimated additional costs to complete activities or the project

Estimate to complete (ETC) refers to the estimated additional costs required to complete activities or the entire project. It represents the projected cost needed to finish the remaining work in the project. This is a crucial measure in project management to ensure that the project stays within budget and resources are allocated appropriately. The original budget for the project (Option A) is the initial baseline cost set for the project and does not necessarily reflect the additional costs needed to complete the project. Costs saved during the project (Option B) would not fall under the estimate to complete as it refers to the savings achieved and not the remaining costs. Total estimated revenue from the project (Option D) is related to the expected income generated from the project and is not associated with the estimated costs required to complete the project.

Get further explanation with Examzify DeepDiveBeta

Total estimated revenue from the project

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy