CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which tool or technique can be used in the control schedule process?

  1. Scheduling tool

  2. Cost-benefit analysis

  3. Stakeholder engagement

  4. Quality audits

The correct answer is: Scheduling tool

The correct answer is A. Scheduling tool. In the control schedule process, scheduling tools, such as Gantt charts, critical path method, or project management software, are commonly used to help monitor and control the project's schedule performance. These tools allow project managers to track progress, identify potential delays, and make necessary adjustments to keep the project on schedule. Options B, C, and D are incorrect because they are not specifically related to the control schedule process. Cost-benefit analysis is more relevant to cost management, stakeholder engagement is related to stakeholder management, and quality audits are part of the quality management processes in a project.