CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which scheduling methods are activity network diagrams used with?

  1. AOA and AON

  2. WBS and OBS

  3. PERT and SWOT

  4. CPM and PDM

The correct answer is: CPM and PDM

Activity Network Diagrams are used with the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT). These methods help project managers to visualize and analyze the sequence of activities, dependencies, and the critical path in a project schedule. AOA (Activity on Arrow) and AON (Activity on Node) are specific types of representations within CPM. Therefore, the correct answer is D, as Activity Network Diagrams are commonly associated with CPM and PERT.