Which is not an output of plan procurement management?

  1. Marketplace conditions

  2. Change requests

  3. Make-or-buy decisions

  4. Procurement statement of work

The correct answer is: Marketplace conditions

Marketplace conditions are not an output of plan procurement management. The Plan Procurement Management process is focused on determining what to procure, when to procure it, how to procure it, and from whom to procure it. This process includes outputs such as procurement management plan, procurement statement of work, make-or-buy decisions, and change requests. However, marketplace conditions are external factors that influence the procurement process but are not considered a direct output of the Plan Procurement Management process.