Which are tools and techniques of create WBS process?

  1. Inspection and audits

  2. Decomposition and expert judgment

  3. Risk analysis

  4. Cost benefit analysis

The correct answer is: Decomposition and expert judgment

The create WBS process involves breaking down project deliverables and work into smaller, more manageable components. This is known as decomposition. Expert judgment is also used in this process to ensure that the WBS is accurate and comprehensive. Inspection and audits are not directly related to creating a WBS, although they may be used later on to ensure the accuracy of the WBS. Risk analysis typically occurs during the planning phase and is not a tool used specifically in creating a WBS. Cost benefit analysis is used to evaluate the value of a project, but is not a tool used in the create WBS process. Therefore, the correct answer is B Decomposition and expert judgment.