CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


When is resource leveling required?

  1. When the project is completed ahead of schedule

  2. When resources are over-utilized

  3. When required resources are only available at certain times or in limited quantities

  4. When the project does not meet quality standards

The correct answer is: When required resources are only available at certain times or in limited quantities

Resource leveling is required when required resources are only available at certain times or in limited quantities. This technique helps in resolving resource allocation conflicts by adjusting the project schedule to ensure that resources are not over-allocated during certain time periods. This ensures a more efficient and effective use of available resources throughout the project duration. Options A, B, and D are not the correct choices because resource leveling is not specifically required in these situations.