What updates come from close procurements?

  1. Change log, affiliation power

  2. Procurement file, deliverable acceptance, lessons learned documentation

  3. Procurement audit outcomes

  4. Stakeholder engagement plans

The correct answer is: Procurement file, deliverable acceptance, lessons learned documentation

The correct answer is B. When a project procurement is completed and closed, the updates include procurement file, deliverable acceptance, and lessons learned documentation. The procurement file is updated to reflect the final outcomes of the procurement process. Deliverable acceptance documentation is updated to confirm that the project deliverables have been accepted according to the procurement terms. Lessons learned documentation is updated to capture any insights or experiences gained during the procurement process that can benefit future projects. Option A is incorrect because the change log and affiliation power are not updates that specifically come from close procurements. Option C is incorrect because procurement audit outcomes are part of the procurement audit process and not specific updates that come from the close procurements. Option D is incorrect because stakeholder engagement plans are not typically updated as a direct result of close procurements but may be updated based on other project activities or changes in stakeholder requirements.