What is the ultimate goal of conducting interviews during the collect requirements process?

  1. To stay on topic with project objectives

  2. To spend time with stakeholders

  3. To complete the project as quickly as possible

  4. To reduce project costs

The correct answer is: To stay on topic with project objectives

The ultimate goal of conducting interviews during the collect requirements process is to stay on topic with project objectives. By conducting interviews with stakeholders, project managers aim to gather relevant and accurate information regarding the project requirements to ensure that the final deliverables align with the project's objectives and meet the stakeholders' expectations. It helps in clarifying any ambiguities, addressing any conflicting requirements, and ensuring that the project stays focused on achieving its intended goals. Conducting interviews is a crucial step in gathering detailed and valuable insights that will guide the project team in successfully delivering the project.