What is the primary purpose of scope management in project management?

  1. Defining the intent of the project and defining the work necessary to complete the project

  2. Monitoring the project budget

  3. Assigning tasks to team members

  4. Evaluating project risks

The correct answer is: Defining the intent of the project and defining the work necessary to complete the project

Scope management in project management is primarily focused on defining the intent of the project and outlining the specific work that needs to be done in order to successfully complete the project. This involves clearly defining the project's objectives, goals, and deliverables, and specifying the tasks and activities that are needed to achieve them. This is in contrast to the other options listed, such as monitoring the budget, assigning tasks to team members, and evaluating project risks, which are all important aspects of project management but are not the primary purpose of scope management.