What is shown in matrix based charts?

  1. Cost allocations across departments

  2. All activities associated with one person and all people with one activity

  3. Statistical analysis of project risks

  4. Timeline of project phases

The correct answer is: All activities associated with one person and all people with one activity

Matrix based charts show all activities associated with one person and all people associated with one activity. This type of chart helps in visualizing the relationships between team members and tasks in a project. Options A, C, and D do not accurately describe what is shown in matrix based charts.