CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is measured by technical performance measurement during project execution?

  1. Financial expenses

  2. Team productivity

  3. Technical accomplishments versus scheduled technical achievement

  4. Progress of risk management

The correct answer is: Technical accomplishments versus scheduled technical achievement

Technical performance measurement during project execution focuses on evaluating technical accomplishments against scheduled technical achievements. This helps in assessing whether the project is progressing as planned in terms of technical goals and milestones. Options A, B, and D do not directly relate to the measurement of technical performance during project execution and are therefore incorrect in this context.