What does the precedence diagramming method (PDM) represent?

  1. The cost associated with each project activity

  2. The time constraints of the project schedule

  3. A schedule model showing activity sequences

  4. The resource allocation for each activity

The correct answer is: A schedule model showing activity sequences

The precedence diagramming method (PDM) is a scheduling technique used in project management to represent the sequence of activities in a project. It shows the logical relationships between project activities, including which activities must be completed before others can start. This method helps in determining the most efficient way to complete a project by identifying dependencies and defining the order in which activities should be executed. Therefore, option C, "A schedule model showing activity sequences," is the correct answer.