What does the critical path method aim to identify?

  1. The shortest path to complete the project

  2. The most cost-effective path to complete the project

  3. The longest sequence of dependent tasks

  4. The most resource-intensive tasks

The correct answer is: The longest sequence of dependent tasks

The critical path method is a project management tool that aims to identify the longest sequence of dependent tasks in a project. This is important because if any of these tasks are delayed, it could delay the entire project. Unlike options A and B, the critical path method does not focus on the shortest or most cost-effective path, but rather the sequence of tasks with the longest duration. Option D is also incorrect as the critical path method does not solely focus on identifying the most resource-intensive tasks, but rather the overall sequence of dependent tasks. Therefore, option C is the correct answer as it accurately describes the goal of the critical path method.