What does the control quality process monitor and record?

  1. Financial transactions only

  2. Quality activities to assess performance

  3. Personnel performance

  4. Stakeholder satisfaction

The correct answer is: Quality activities to assess performance

The control quality process in project management monitors and records quality activities to assess performance. This process involves comparing actual project results with quality standards to ensure that deliverables meet the quality requirements set out in the quality management plan. By monitoring and recording quality activities, project managers can identify any deviations from the quality standards and take corrective action as needed to ensure that the project deliverables meet the required quality levels. This process is crucial in ensuring the overall success of the project by maintaining the quality of deliverables throughout the project lifecycle. The other options are incorrect because the control quality process specifically focuses on assessing the performance of quality activities and ensuring that project deliverables meet quality standards, rather than monitoring financial transactions, personnel performance, or stakeholder satisfaction.