CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does 'lead' (negative lag) mean in project scheduling?

  1. The amount of time a project is ahead of schedule

  2. Amount of time a successor's start or finish can occur before the predecessor's start or finish

  3. The acceleration of a project phase

  4. Lead time required to acquire project resources

The correct answer is: Amount of time a successor's start or finish can occur before the predecessor's start or finish

In project scheduling, 'lead' (negative lag) refers to the amount of time a successor's start or finish can occur before the predecessor's start or finish. This means that the successor activity can begin or finish before the predecessor activity, allowing for overlap and potentially saving time in the project schedule. Option A is incorrect because it describes being ahead of schedule in general, not specifically in the context of predecessor and successor activities. Option C is incorrect because it refers to accelerating a project phase as a whole, not specifically the relationship between predecessor and successor activities. Option D is incorrect because it mentions the lead time required to acquire project resources, which is a different concept unrelated to the scheduling relationship between tasks.