CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does Actual Cost (AC) include?

  1. Only direct costs incurred during a given period

  2. Projected costs at the end of the project

  3. The total of direct and indirect costs incurred in accomplishing work during a given period

  4. Only indirect costs incurred during a given period

The correct answer is: The total of direct and indirect costs incurred in accomplishing work during a given period

Actual Cost (AC) includes the total of direct and indirect costs incurred in accomplishing work during a given period. Direct costs are expenses that can be traced directly to a specific project, such as materials and labor costs. Indirect costs are expenses that are not directly accountable to a specific project but are necessary for the general operation of the project, such as utilities or office rent. Therefore, the correct answer is C because Actual Cost (AC) encompasses both direct and indirect costs incurred during the project.