What does a procurement statement of work typically develop from?

  1. Project scope baseline

  2. Work breakdown structure

  3. Market research results

  4. Project management plan

The correct answer is: Project scope baseline

A procurement statement of work typically develops from the project scope baseline. It is important to understand that the project scope baseline defines what work needs to be done and what deliverables are required. Therefore, the procurement statement of work is built upon this baseline to clearly communicate the requirements and expectations to potential vendors or contractors. Option B, the work breakdown structure, is a hierarchical decomposition of the total scope of work to be carried out by the project team. While the work breakdown structure is a critical component in project management, the procurement statement of work is specifically derived from the project scope baseline. Option C, market research results, may influence the procurement process by providing insights into potential vendors, pricing, or industry standards. However, the procurement statement of work is primarily developed based on the project scope baseline rather than market research results. Option D, the project management plan, is a comprehensive document that outlines how the project will be executed, monitored, and controlled. While the project management plan is a key document in project management, the procurement statement of work is specifically linked to the project scope baseline.