CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What do resource calendars identify?

  1. The cost of resources

  2. The skill level of resources

  3. Working days and shifts resources are available

  4. The total quantity of resources needed

The correct answer is: Working days and shifts resources are available

Resource calendars identify the working days and shifts during which resources are available for project work. This information helps in scheduling tasks effectively based on resource availability. The resource calendar does not primarily focus on the cost of resources (option A), the skill level of resources (option B), or the total quantity of resources needed (option D), although these factors can be important considerations in project management as well.