What do process boundaries describe?

  1. Purpose, start and end, inputs and outputs, owner, and stakeholders of the process

  2. The forces for and against change

  3. The statistical methods for experiments

  4. The way to measure project progress

The correct answer is: Purpose, start and end, inputs and outputs, owner, and stakeholders of the process

Process boundaries describe the purpose, start and end, inputs and outputs, owner, and stakeholders of the process. Option B is incorrect because process boundaries do not describe forces for and against change. Option C is incorrect because process boundaries do not refer to statistical methods for experiments. Option D is incorrect because process boundaries do not describe the way to measure project progress.