CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What do mandatory dependencies represent?

  1. Dependencies that cannot be changed

  2. External factors affecting the project

  3. Internal relationships within the project

  4. Options for different activity orders

The correct answer is: Dependencies that cannot be changed

Mandatory dependencies represent dependencies that cannot be changed. These dependencies are inherent to the nature of the project activities and must be completed in a specific order. They are often related to technical limitations, contractual obligations, or even physical constraints. As such, they are not optional or flexible and must be adhered to for the successful completion of the project. Options B, C, and D are incorrect because: - Option B, external factors affecting the project, refers to dependencies that are outside the control of the project team, not dependencies that cannot be changed. - Option C, internal relationships within the project, while important, do not specifically refer to dependencies that cannot be changed. - Option D, options for different activity orders, suggests flexibility in sequencing activities, which is contrary to the concept of mandatory dependencies where the sequence is fixed and must be followed.