CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What best describes a schedule activity?

  1. A task larger than a project phase

  2. An element of work performed during the course of a project

  3. A high-level overview of all project tasks

  4. A tool used for estimating project duration

The correct answer is: An element of work performed during the course of a project

A schedule activity is an element of work that is performed during the course of a project. It is a specific task or action that needs to be completed in order to move a project forward and achieve its objectives. Option A is incorrect because a project phase can include multiple tasks and activities. Option C is incorrect because a high-level overview does not necessarily include specific tasks and actions. Option D is incorrect because a schedule activity is not a tool used for estimating project duration, but rather a specific action that contributes to the overall project duration.