CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Certified Associate in Project Management Exam with practice questions and answers. Enhance your understanding of project management principles and strategies to excel in the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


How is Schedule Variance (SV) calculated?

  1. SV = PV - EV

  2. SV = EV - PV

  3. SV = AC - PV

  4. SV = PV + EV

The correct answer is: SV = EV - PV

Schedule Variance (SV) is calculated by subtracting the Planned Value (PV) from the Earned Value (EV). This calculation helps in determining whether a project is ahead of or behind the planned schedule at a specific point in time. In this case, SV = EV - PV is the correct formula. Option A (SV = PV - EV) is incorrect as it would result in a negative value, which does not accurately represent schedule variance. Option C (SV = AC - PV) involves comparing the Actual Cost (AC) with the Planned Value (PV) and is related to Cost Variance, not Schedule Variance. Option D (SV = PV + EV) is also incorrect because adding PV to EV does not provide an accurate representation of the variance between the planned and earned values in the schedule.