During which phase do team members learn about the project and their formal roles for the first time?

  1. Forming

  2. Storming

  3. Norming

  4. Executing

The correct answer is: Forming

During the Forming phase is when team members learn about the project and their formal roles for the first time. This phase is characterized by team members getting acquainted with each other, understanding the project objectives, and beginning to define their roles and responsibilities within the team. The Storming phase involves conflict resolution, the Norming phase focuses on strengthening relationships and increasing cohesion among team members, and the Executing phase is when the project work is performed according to the project management plan.